When you export job from Project Menu:
a) You can import jobs into a higher version using Project/Export.
b) Using v0-API.
c) Using v1-API.
d) It’s the only way to back up jobs.
can anyone give the answer I am confused
Please find my response based on what I understood from you question:
When you export job from Project Menu:
a) You can import jobs into a higher version using Project/Export. - CORRECT (Vice versa is not allowed i.e. Higher to Lower)
b) Using v0-API - INCORRECT
c) Using v1-API - INCORRECT (This API can import but exporting way is different than project menu)
d) It’s the only way to back up jobs - INCORRECT ( Its an alternate way to backup)